On Thursday April 30, 2020, a site visit was organized for the Togo Invest team by KEKELI Efficient Power (KEP) General Management.
This visit made it possible to observe the good progress of the civil engineering works, in accordance with the schedule and according to safety standards.
The work is carried out by VINCI under the supervision of TSK, in charge of the construction of the thermal power plant.
As a reminder, Togo Invest is a shareholder in the KIFEMA CAPITAL investment vehicle, which holds 25% of the project company Kekeli Efficient Power (KEP).
The main shareholder of KEP is the ERANOVE group, up to 75%.